Location: UK
Type: Specialist Installations
Client: Spie Matthew Hall
Duration: 16 weeks
Cost: £0.8 Million
Overview:
The front of house works including heat recovery and VRV installation was fully designed and installed in house.
The data hall with 2.1 mega watts of cooling, pressure relief ductwork, gas extract and plant room ventilation has been completed in 16 weeks.
Scope of works:
— Design, installation of front of house VRV/ventilation
— Plumbing services
— CRAC unit and pipe work installation
— Pressure relief ductwork
— Gas extract ductwork
— Plant room ventilation
— Battery room cooling
— Leak detection
— Mechanical control panels/wiring
— Full commissioning.