KPMG Gateway House

  • Location: Eastleigh
  • Client: Paramount Office Interiors
  • Duration: 17 Weeks
  • Cost: £500,000
  • Sector: Commercial
KPMG Gateway House
KPMG Gateway House
KPMG Gateway House

Our Challenge

S & G Air Conditioning Contracts Ltd were employed to install new Mechanical Services and modifications to existing services serving the office areas and new catering facilities on the 3rd floor.

Our Solution

Our scope of works included the following:

  • Design Responsibility
  • Modifications and installation of ventilation to accommodate new layout
  • Modifications of the existing Mitsubishi VRF system to accommodate new layout
  • Installation of specialist server room cooling systems
  • New chilled water pipework
  • Supply and Installation of BMS
  • Supply and Installation of New Catering AHU
  • Supply and Installation of domestic water system and pipework for new catering facility